An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of
An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of 15 days. Find its STANDARD DEVIATION.
Group of answer choices
2.5 days
1 day
2 days
1.5 days
0.5 day