Question

1 Approved Answer

An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of

An activity on a PERT network has an optimistic time of 6 days, a most likely time of 12 days, and a pessimistic time of 15 days. Find its STANDARD DEVIATION.

Group of answer choices

2.5 days

1 day

2 days

1.5 days

0.5 day

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Alan Bryman, Emma Bell

3rd Edition

0199583404, 9780199583409

More Books

Students also viewed these General Management questions

Question

Graph the given functions. L = 3e e 3

Answered: 1 week ago

Question

Brief the importance of span of control and its concepts.

Answered: 1 week ago

Question

What is meant by decentralisation?

Answered: 1 week ago

Question

Write down the Limitation of Beer - Lamberts law?

Answered: 1 week ago

Question

Discuss the Hawthorne experiments in detail

Answered: 1 week ago