Question
1 Approved Answer

A project comprises of activities A, B, C, D, E, F. The duration of project is 210 days. The duration for activity D is 61

A project comprises of activities A, B, C, D, E, F. The duration of project is 210 days. The duration for activity D is 61 days and it has the slack of 11 days. Suppose activity D is delayed and no other activity is delayed. As a result of this delay in D, the project duration increased by 50 days. What is the delay (in number of days) in activity D

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Marketing Management

Authors: Robert D Reid, David C Bojanic

4th Edition

0471476544, 9780471476542

More Books

Students explore these related General Management questions