Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project comprises of activities A, B, C, D, E, F. The duration of project is 60 days. The duration for activity D is 15
A project comprises of activities A, B, C, D, E, F. The duration of project is 60 days. The duration for activity D is 15 days and it has the slack of 9 days. Suppose activity D is delayed by 17 days and no other activity is delayed. As a result of this delay in D, what is the new project duration
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started