A project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion

  1. A project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion time is 8.

OptimisticMost ProbablePessimistic
ActivityTime (hr)Time (hr)Time (hr)
A Floor sanding345
B Paint mixing0.511.5
C Ceiling painting15.57
D Wall painting129
E Floor buffing123

image text in transcribed
FLOOR FLOOR SANDING BUFFING PAINT START CEILING FINISH PAINT MIXING PAINT WALLS

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Algebra And Trigonometry

Authors: Michael Sullivan

10th Edition

0321999290, 9780321999290

More Books

Students also viewed these Mathematics questions