A project consists of seven activities. The following table shows the estimated time of the activities and the precedence relations. Activity Estimated durations ( days
A project consists of seven activities. The following table shows the estimated time of the activities and the precedence relations.
Activity
Estimated durations days
Immediate predecessor
A
B
C
A
D
A
E
B C
F
B C
G
D E
What is the earliest project completion time?