A project had a budget of $635K and was completed on time. The project expenses were 9 percent less than what the project called for.
A project had a budget of $635K and was completed on time. The project expenses were 9 percent less than what the project called for. What is the cost variance at completion for this project? (Pick closest answer)
(a) $-57K(
b) $57K
(c) $578K
(d) $692