A project has a cost performance index of 0.6. All activities were completed on time except one work package. The workpackage was for design work

A project has a cost performance index of 0.6. All activities were completed on time except one work package. The workpackage was for design work and could not be done because the expert resource was unavialbale till now. Now the project manager has to calculate the estimate to complete for the remaining work. Which approach should he take

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Management In Construction Projects

Authors: Abdul Razzak Rumane

2nd Edition

0367890038, 978-0367890032

More Books

Students also viewed these General Management questions

Question

4.3 Describe the job analysis process and methods.

Answered: 1 week ago