Question

1 Approved Answer

A Project has a PV of $60,000 at the status date of 10 months and a BAC of $185,000 at the end of the project.

A Project has a PV of $60,000 at the status date of 10 months and a BAC of $185,000 at the end of the project. The Project schedule is 19 months and at the status date AC is $115,000 and EV for the project of $48,000
The project sponsor wants to know what the ETCdur forecast is IN MONTHS if a new EAC$ is used for revised funding, assuming the project will continue the way it's currently going. 

 

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions

Question

What memories does the character have that relate?

Answered: 1 week ago

Question

How were these childhood messages delivered? What events occurred?

Answered: 1 week ago