A project has an original total of $1,000,000. At month 10, the AC is $800,000. Suppose CPI=0.87, and SPI=0.93. Calculate EAC under the situation that
A project has an original total of $1,000,000. At month 10, the AC is $800,000. Suppose CPI=0.87, and SPI=0.93. Calculate EAC under the situation that the project continues under the same conditions as experienced to date and then calculate the ETC and VAC.
Step by Step Solution
There are 3 Steps involved in it
Step: 1