Question
1 Approved Answer
A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and
A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and cash inflows of $350 a year for three years. If the start is delayed one year, the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?
Select one:
a. $.70
b. $1.08
c. $1.67
d. $2.20
e. $.20