A project has been defined to contain the following activities, along with their time estimates for their completion. What is the value of Z?
A project has been defined to contain the following activities, along with their time estimates for their completion. What is the value of Z? IMMEDIATE OPTIMISTIC MOST PESSIMISTIC ACTIVITY LIKELY PREDECESSOR DURATION DURATION DURATION A 1 4 7 B A 2 6 7 C D 3 4 6 D A 6 12 14 E D 3 6 12 F B,C 6 8 16 G E.F 1 6