Question
A project has been defined to contain the following list of activities, along with their required times for completion: Activity Immediate Predecessors Time (Days) A
A project has been defined to contain the following list of activities, along with their required times for completion:
Activity | Immediate Predecessors | Time (Days) |
A | - | 1 |
B | A | 3 |
C | A | 5 |
D | B | 3 |
E | C, D | 6 |
F | C | 4 |
G | E, F | 3 |
Draw the critical path diagram. (4 points)
Show the early start, early finish, late start, and late finish times. (4 points)
What is the critical path? (2 points)
How long will it take to complete the project? (2 Points)
Due to unavailable resources, Task C will be delayed by 2 days. Does this have an impact of the total number of days required to complete the project? Explain your answer. (3 points)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started