Question
1 Approved Answer
A project has estimated annual net cash flows of $13,750 for two years and is estimated to cost $45,000. Assume a minimum acceptable rate of
A project has estimated annual net cash flows of $13,750 for two years and is estimated to cost $45,000. Assume a minimum acceptable rate of return of 6%. Use the Present Value of an Annuity of $1 at Compound Interest table below.
Present Value of an Annuity of $1 at Compound Interest | |||||
Year | 6% | 10% | 12% | 15% | 20% |
1 | 0.943 | 0.909 | 0.893 | 0.870 | 0.833 |
2 | 1.833 | 1.736 | 1.690 | 1.626 | 1.528 |
3 | 2.673 | 2.487 | 2.402 | 2.283 | 2.106 |
4 | 3.465 | 3.170 | 3.037 | 2.855 | 2.589 |
5 | 4.212 | 3.791 | 3.605 | 3.352 | 2.991 |
6 | 4.917 | 4.355 | 4.111 | 3.784 | 3.326 |
7 | 5.582 | 4.868 | 4.564 | 4.160 | 3.605 |
8 | 6.210 | 5.335 | 4.968 | 4.487 | 3.837 |
9 | 6.802 | 5.759 | 5.328 | 4.772 | 4.031 |
10 | 7.360 | 6.145 | 5.650 | 5.019 | 4.192 |
Determine (1) the net present value of the project (if required, round to the nearest dollar) and (2) the present value index (rounded to two decimal places). If required, use the minus sign to indicate a negative net present value.
(1) Net present value of the project | $fill in the blank 1 |
(2) Present value index | fill in the blank 2 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started