A project has estimated sales of 11,500 units, 2 percent. The expected variable cost per unit is $13, and the expected fixed costs are $29,000.
A project has estimated sales of 11,500 units, 2 percent. The expected variable cost per unit is $13, and the expected fixed costs are $29,000. The fixed and variable cost estimates are considered accurate within a range of 3 percent. The sales price is estimated at $29 a unit, 1 percent. What is the contribution margin for a sensitivity analysis using a fixed cost of $30,000?