Question

1 Approved Answer

A project has estinated annual net cash flows of $56,300. It is estimated to cost $585,520. Determine the cash payback period. Round the answer to

image text in transcribed
A project has estinated annual net cash flows of $56,300. It is estimated to cost $585,520. Determine the cash payback period. Round the answer to one decimal place. years