A project has four critical activities, A, B, C and D. All the activities are estimated to
Fantastic news! We've Found the answer you've been seeking!
Question:
A project has four critical activities, A, B, C and D. All the activities are estimated to require similar effort of 5 days each and cost $5,000 per activity. After day 11 Activity A and B are complete; Activity C is 50% complete and $13,000 has already been spent. What is Cost Performance Index (CPI) for the project?
Question 3 options:
a)
1.2
b)
0.96
c)
1.00
d)
1.04
Posted Date: