Question

1 Approved Answer

A project has four critical activities, A, B, C and D. All the activities are estimated to require similar effort of 5 days each and

A project has four critical activities, A, B, C and D. All the activities are estimated to require similar effort of 5 days each and cost $5,000 per activity. After day 11 Activity A and B are complete; Activity C is 50% complete and $13,000 has already been spent. What is Cost Performance Index (CPI) for the project?

Question 3 options:

a)

1.2

b)

0.96

c)

1.00

d)

1.04

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Organization

Authors: V Carl Hamacher, Carl Hamacher, Zvonko G Vranesic, Safwat G Zaky

5th Edition

0072320869, 9780072320862

More Books

Students also viewed these General Management questions

Question

Show enthusiasm for the position (but not too much).

Answered: 1 week ago

Question

Personal role: This consists of service to family and friends.

Answered: 1 week ago

Question

The role of life: It consists of your own service to yourself.

Answered: 1 week ago