A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9.5, 19, 28.5 ),

A project has four major activities. 

Activity A precedes activity B, activity C precedes activity D. 

3-point estimates for activities are

A(9.5, 19, 28.5 ), 

B( 4.5, 9, 13.5 ), 

C( 2, 2, 2 ), 

D( 3, 3, 3 ) weeks. 

What probability would you assign to a project duration of more than 28 weeks? 

Select one: 

a. 0.3388 

b. 1 

c. 0.5 

d. 0.8645

Step by Step Solution

3.33 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

Critical path ab which has a duration of 28 weeks 199 The probability will be determined b... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

OM4 operations management

Authors: David Alan Collier, James R. Evans

4th edition

1133372422, 978-1285701011, 1285701011, 978-0357228739, 978-1133372424

More Books

Students also viewed these Accounting questions

Question

explain why both internal and external recovery are important;

Answered: 1 week ago

Question

600 lb 20 0.5 ft 30 30 5 ft

Answered: 1 week ago