Question
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9.5, 19, 28.5 ),
A project has four major activities.
Activity A precedes activity B, activity C precedes activity D.
3-point estimates for activities are
A(9.5, 19, 28.5 ),
B( 4.5, 9, 13.5 ),
C( 2, 2, 2 ),
D( 3, 3, 3 ) weeks.
What probability would you assign to a project duration of more than 28 weeks?
Select one:
a. 0.3388
b. 1
c. 0.5
d. 0.8645
Step by Step Solution
3.33 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
Critical path ab which has a duration of 28 weeks 199 The probability will be determined b...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
OM4 operations management
Authors: David Alan Collier, James R. Evans
4th edition
1133372422, 978-1285701011, 1285701011, 978-0357228739, 978-1133372424
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App