A project has FOUR tasks A, B, C and D respectively as detailed below. Lets assume its Nov. 28 today and we are doing the
A project has FOUR tasks A, B, C and D respectively as detailed below. Lets assume its Nov. 28 today and we are doing the analysis up to the current point (today) [monitoring date]. How efficient should this project team be to finish within the allocated budget? Use the earned value approach. Assumptions: Lets say that after discussions with the applicable project team members and inspection of the progress, it was determined that the first task was 80% complete, the second task was 65% complete and task C was completed at 15 % on the monitoring date. Actual cost of first task is $ 37,500, the second task is $ 20,000 and the third task is $ 2,500.
ID | NAME | START | END | BUDGET |
A | Procure materials | Nov 1 | Dec 5 | $40 000 |
B | Finalise plans | Nov 5 | Dec 8 | $25 000 |
C | Finalise resources | Nov 15 | Dec 12 | $7500 |
D | Build model | Nov 22 | Dec 31 | $75 000 |
TOTAL | $147 500 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started