A project has the activities, predecessors and normal times (in weeks) shown in the table below. Activity Predecessor Normal Time (weeks) A 2 B A
A project has the activities, predecessors and normal times (in weeks) shown in the table below.
Activity | Predecessor | Normal Time (weeks) |
A | 2 | |
B | A | 3 |
C | A | 2 |
D | C | 6 |
E | B | 1 |
F | E and D | 2 |
Develop an Activity-on-node diagram (no need to submit), and then fill the table below:
Answer:
Activity | Early start | Early finish | Late start | Late finish | Slack |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started