Question

1 Approved Answer

A project has the activities, predecessors and normal times (in weeks) shown in the table below. Activity Predecessor Normal Time (weeks) A 2 B A

A project has the activities, predecessors and normal times (in weeks) shown in the table below.

Activity Predecessor Normal Time (weeks)
A 2
B A 3
C A 2
D C 6
E B 1
F E and D 2

Develop an Activity-on-node diagram (no need to submit), and then fill the table below:

Answer:

Activity Early start Early finish Late start Late finish Slack
A
B
C
D
E
F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

1st Edition

0749486198, 978-0749486198

More Books

Students also viewed these General Management questions