Question
1 Approved Answer
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250
- A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the cost of the least expensive project possible?
Activity Normal time Crash time Normal Cost Crash cost Predecessor
A 8 5 1,000 2,000
B 6 4 1,500 2,000 A
C 8 5 1,800 2,300 A
D 12 9 1,000 1,800 B
E 14 11 950 1,450 B
F 9 7 1,500 1,900 C, D
G 7 5 2,300 2,800 E, F
Answers : $11,450 $13,450 $12,450 $14,450
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started