A project has the following Activities, Activity times, and predecessors. Predecessor Activity Time A 3 A 3 2 B IC 4 A N D B
A project has the following Activities, Activity times, and predecessors. Predecessor Activity Time A 3 A 3 2 B IC 4 A N D B 4 3 E CD The minimum possible completion time is A. 16 B. 9 C. 10 D. 8 E. 4 HI