A project has the following activities, precedence relationships, and time estimates in weeks: Activity Immediate Predecessor Activities Optimistic Time ( t o) Most Likely Time
A project has the following activities, precedence relationships, and time estimates in weeks:
Activity | Immediate Predecessor Activities | Optimistic Time (to) | Most Likely Time (tm) | Pessimistic Time (tp) |
A | -- | 15 | 20 | 25 |
B | -- | 8 | 10 | 12 |
C | A | 25 | 30 | 40 |
D | B | 15 | 15 | 15 |
E | B | 22 | 25 | 27 |
F | E | 15 | 20 | 22 |
G | D | 20 | 20 | 22 |
a. Determine the critical path and the expected duration of the project.
b. What is the probability that the project will take less than 57 weeks to complete?
c. What is the minimum time when you are 80% confident that the project will complete?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started