A project has the following activities, with specified precedents and expected durations (in hours). How much slack does activity E have? Activity Precedent Duration A
A project has the following activities, with specified precedents and expected durations (in hours). How much slack does activity E have?
Activity | Precedent | Duration |
A | - | 6.0 |
B | - | 7.2 |
C | A | 4.8 |
D | B, C | 6.0 |
E | B, C | 4.5 |
F | D | 7.7 |
G | E, F | 4.0 |