A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The
A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the projects PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to the expected cash flow in each year? d. Explain why this ratio declines.