A project has the following information: Actual Cost Task Duration%Work Complete!Original Budget (to Date) 88% 84%) 3196| $36934$37738 $4148 $50633$44497 Research 6 days Initial Design
A project has the following information: Actual Cost Task Duration%Work Complete!Original Budget (to Date) 88% 84%) 3196| $36934$37738 $4148 $50633$44497 Research 6 days Initial Design 3 days Prototype 18 days What is the Earned Value (EV) for the Initial Design task? Enter your answer as: 1234 Round your answer. Do not use a dollar sign "$"), any commas(" or a decimal point