Question
A project has the following paths: A-D-F (15 days) B-D-F (12 days) C-E-F (14 days) and the crash cost per day for each of the
A project has the following paths:
A-D-F (15 days) B-D-F (12 days) C-E-F (14 days)
and the crash cost per day for each of the activities are
Activity | Crash Cost $/day |
---|---|
A | $1,100 |
B | $1,500 |
C | $1,100 |
D | $800 |
E | $500 |
F | $750 |
Assume that indirect project costs are $1,000 per day; for which activities would the total project cost (direct plus indirect) be reduced if that activity were crashed by one day? [This is only asking whether or not, for each activity considered individually, that activity would reduce the total cost of the project if the activity were crashed by a day; select ALL that would.]
A.
Activity A
B.
Activity B
C.
Activity C
D.
Activity D
E.
Activity E
F.
Activity F
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started