A project has the following progress. [ 2 5 ] Planned project length is 6 months. Project budget is $ 1 , 2 0 0

A project has the following progress. [25]
Planned project length is 6 months.
Project budget is $1,200,000.
Time worked to date is 3 months.
Actual cost to date is $550,000.
Percentage of the planned project to be completed is 50%.
Actual percentage of the project completed is 35%.
Determined the planned value. [4]
Determine the earned value. [4]
Determine the Schedule variance. [4]
What is the schedule performance? [4]
Are we behind or ahead of schedule? [4]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bears Of The World Ecology Conservation And Management

Authors: Vincenzo Penteriani, Mario Melletti

1st Edition

1108483526, 978-1108483520

More Books

Students also viewed these General Management questions