Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion of the whole
A project is estimated to complete in 6 months. Refer to the table below. The total budgeted cost is $ till completion of the whole project. The cumulative budgeted cost is $ at the end of month 4. Month TBC 1 2 3 4 5 6 Task 1 $15 $5 $10 Task 2 $50 $10 $10 $15 $15 Task 3 $50 $10 $20 $20 Total Cumulative (II) Below is a table of actual costs. The cumulative actual cost is $at the end of month 4. Is there a cost overrun? (note: please fill in Yes or No). Month 1 2 3 4 Task 1 $6 $9 Task 2 $10 $10 Task 3 $5 Total Cumulative (III) Below is a table of the cumulative percentages of work completed by the end of month 4. The cumulative earned value of the project is $ at the end of month 4. Month 1 2 3 4 Task 1 30 100 Task 2 10 20 Task 3 10 (Amounts are cumulative percent complete) (IV) At the end of month 4, CPI= , (Note: keep two decimals) and CV= . (V) If the project team guarantees that starting from month 5 they will finish.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Answer Yes there is a cost overrun Explanation To det...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started