You are the contracting officer for contract W0054219P0052 Actions for the delivery of five rail carts. Two weeks after the contract was awarded, the requiring

You are the contracting officer for contract W0054219P0052

Actions

 for the delivery of five rail carts.  Two weeks after the contract was awarded, the requiring activity informed you that they need to add two additional characteristics to the salient characteristics in Attachment 0001.  These additional characteristics will change the form, fit, and function of the rail carts.  The requiring activity is willing to change the delivery date to 30 days later than the current schedule as part of the Government's consideration for the contractor, Acme, accommodating this change.

  1. How could you execute the requiring activity's request for a change? (citation not required)

Step by Step Solution

3.44 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

As the contracting officer for contract W0054219P0052 to execute the requiring activitys request for a change you would follow these steps Confirm the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Smith and Roberson Business Law

Authors: Richard A. Mann, Barry S. Roberts

15th Edition

1285141903, 1285141903, 9781285141909, 978-0538473637

More Books

Students also viewed these General Management questions

Question

Define Heideggers terms throwness, Mitwelt, and Umwelt.

Answered: 1 week ago

Question

Describe the differences between law and ethics.

Answered: 1 week ago