Question
You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from the requiring
You are the contracting officer for contract W0054219P0052 for the delivery of five rail carts. One month after award, you receive notice from the requiring activity that the rail cars need to be delivered to El Paso, TX instead of San Antonio, TX. There will be no change to the required delivery date.
- Is this proposed change within the general scope of the current contract? (citation not required)
2. How could you execute the requiring activity's request for a change?
3 . If this change will be accomplished through a modification to the current contract, will the modification be executed as a unilateral or a bilateral modification?
4.What is the authority for the modification?
Step by Step Solution
3.41 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
1 Yes the proposed change to deliver the rail carts to El Paso TX instead of San Antonio TX without any change to the required delivery date is likely ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started