A project is estimated to cost 70,000 with a timeline of 50 days. After 30 days, the PM finds 50,000 worth of work has been
A project is estimated to cost 70,000 with a timeline of 50 days. After 30 days, the PM finds 50,000 worth of work has been completed and 30,000 spent. What is the Cost Performance Index (CPI)?