A project is scheduled to be completed within 16 months and the total cost of the project is 200,000 USD. Eight months have passed, and
A project is scheduled to be completed within 16 months and the total cost of the project is 200,000 USD. Eight months have passed, and 110,000 USD has been spent. After a closer review, you (as a pro