Question

1 Approved Answer

A project is scheduled to have 5 people full-time and take 24 weeks. What happens to the schedule if you increase the number of people

A project is scheduled to have 5 people full-time and take 24 weeks.

What happens to the schedule if you increase the number of people to 10? I assume that double the workers will result in 2.4 weeks to complete the project.

Isthis correct? if so, explain.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

No the assumption that doubling the number of people will result in the project being completed in 2... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions

Question

(c) Calculate a 90% upper confidence limit for the error variance .

Answered: 1 week ago