A project is supposed to last 100 days and allocated budget is $400,000 . At 50 th day, project was monitored and was found to
A project is supposed to last 100 days and allocated budget is
$400,000
. At 50 th day, project was monitored and was found to be
50%
percent complete and actual cost was incurred was
$300,000
. What would you say about the project's progress?\ a. Propect has incurred mote cost than planned.\ b. Project has incurred less cost than planned.\ c. Can't say anything