A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead.

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead. The requested
workaround will introduce delays and require additional budget.
What should the project manager do?
Discuss the options with the client as part of the change control process.
Mitigate risks associated with the workaround to avoid project delays.
Request to use the management reserve to keep the schedule.
Proceed with the approved risk response plan.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Encompassing The Future Offshore Oil And Gas Operations Environment Health And Safety Performance Management Policy Economics Law And Environment

Authors: William J. Cairns; Ann G Wilkie; Judith Hackitt; Peter Hepburn; Ewan MacAngus; Rita Marcella; Hayley

1st Edition

1999766210, 9781999766214

More Books

Students also viewed these General Management questions

Question

=+1. What is the relationship among property rights,

Answered: 1 week ago