A project manager does not have the necessary time to do the planning, and the deadline to start is approaching. Consequently, it seeks to plan

A project manager does not have the necessary time to do the planning, and the deadline to start is approaching. Consequently, it seeks to plan in the most effective way possible. What advice would you offer? Explain the following and the right answer.

a. Make sure he has a signed Project Charter and start with the WBS.

b. Create a list of activities before creating a network diagram.

c. Document all known risks before documenting high-level assumptions.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David M Kroenke, Randall J Boyle

7th Edition

0134402197, 9780134402192

More Books

Students also viewed these General Management questions

Question

4. What is the goal of the others in the network?

Answered: 1 week ago

Question

2. What we can learn from the past

Answered: 1 week ago