A project manager is overseeing a project with a total budget of $4,000,000. The project is halfway through its timeline with the following costs incurred:
A project manager is overseeing a project with a total budget of $4,000,000. The project is halfway through its timeline with the following costs incurred:
- Actual Costs to Date: $2,000,000
- Planned Value to Date: $2,100,000
- Earned Value to Date: $1,900,000
Questions:
- Calculate the Cost Performance Index (CPI) and Schedule Performance Index (SPI).
- Based on CPI and SPI, evaluate the project’s performance and suggest corrective actions if needed.
- Forecast the total cost at completion using the CPI.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started