A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What
A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next? Quality process Organizational process assets (OPAs) Project charter Quality management plan