Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project manager working with her team has developed the following list of tasks and estimates of duration time. Create a AON diagram, identify the
A project manager working with her team has developed the following list of tasks and estimates of duration time.
Create a AON diagram, identify the critical path and calculate the expected project duration
Estimate the additional weeks she requires to be 95% confident of completion date
If the customer requests the project be delivered a week early, what is the chance that it can be done with the same resources?
Task | Predecessors | T optimistic | T Most Likely | T Pessimistic |
A | 3 | 4 | 5 | |
B | A | 4 | 8 | 15 |
C | A | 2 | 4 | 6 |
D | A | 4 | 8 | 12 |
E | B | 7 | 9 | 14 |
F | C,B | 2 | 5 | 8 |
G | E,D | 5 | 7 | 12 |
H | F,G, I | 4 | 7 | 10 |
I | D | 3 | 6 | 9 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started