A project progressing on time and within budget is 30 days away from achieving its main milestone. The project manager then learns that a key
A project progressing on time and within budget is 30 days away from achieving its main milestone. The project manager then learns that a key component to achieve this milestone will be unavailable for 45 days. What should the project manager do? Question 21 options: 1) Revise the risk management plan 2) update the issue log 3) notify stakeholders at the next project status meeting 4) send an amended progress report to all stakeholders