Question
1 Approved Answer
A project returns 15% when the market returns 10% and 8% when the market returns 15%. Calculate the projects market beta A. +0.7 B. -0.7
A project returns 15% when the market returns 10% and 8% when the market returns 15%. Calculate the projects market beta
A. +0.7
B. -0.7
C. -1.4
D. 0.0