A project team has completed, and the customer has accepted, the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project?
The project is incomplete because the project needs to be replanned.
The project is complete because the project has reached the due date.
The project is complete because the customer has accepted the deliverables.
The project is incomplete until all projects and deliverables are complete and accepted.