A project team is currently investigating an issue on your project. The team wants to setup a visual management tool to track and monitor the
A project team is currently investigating an issue on your project. The team wants to setup a visual management tool to track and monitor the work in progress and to understand scheduling demands of the project. Which of the following tools will you recommend to be used? * WBS * Fishbone diagram * Kanban board * Product backlog