A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages.
However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
Create a lessons learned register to include operations team training for future projects.
Prepare detailed documentation to be shared with the operations team during project closure.
Include knowledge transfer sessions between the project and operations teams at every stage.
Change the project management plan to add a final stage for product handoff to the operations team.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started