Question
1 Approved Answer
A project will cost $204,661.00 today. The project is then expected to generate after-tax cash flows of $30,000.00 per year. An economist also projects that
A project will cost $204,661.00 today. The project is then expected to generate after-tax cash flows of $30,000.00 per year. An economist also projects that the project will create synergies with other products for the firm and the synergies will create an after-tax cash flow of $12,261.00 per year. The cost of capital for the firm is 10.00%. The firm will run the project for 11.00 years. What is the NPV of this project?