A project's critical path is composed of activities A ( variance 0 . 3 3 ) , B ( variance 0 . 6 7 )

A project's critical path is composed of activities A(variance 0.33),B(variance 0.67),C(variance 0.33), and D (variance 0.17).
What is the standard deviation on the critical path?
a) None of them
b)3.27
c)1.50
d)1.22
Bo brak
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Aided Database Design

Authors: Antonio Albano, Valeria De Antonellis, A. Di Leva

1st Edition

0444877355, 978-0444877352

More Books

Students also viewed these Databases questions