Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project's current total Earned Value (EV) is 150,000 and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the project?
A project's current total Earned Value (EV) is 150,000and the Actual Cost (AC) is 100,000. What is the Cost Variance (CV) of the project?
A project is estimated to cost 50,000 with a timeline of50 days. After 25 days, the project manager finds thatactual cost is 50,000. What is the Cost Performance Index (CPI)?
7. What is EAC for the project if BAC = 50,000AC=10,000 EV = 7,000, ETC=50,000
What is the best way to calculate the Estimate AtCompletion (EAC) when original estimates are no longer valid.
Compute SPI, CPI Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are
Budget At Completion (BAC) = $40,000
Earned Value (EV) = $26,000
Planned Value (PV) = $20,000
Actual Cost (AC) = $25,000
You are the project manager on a project that has $500,000 software development effort. There are two teams of programmers that will work for six month for a total of 8,000 hours. According to the project schedule your team should be done with 48% of the work. As of today, the project is 30% complete while 60% budget has been used. Calculate and share your conclusion
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started