A project's deliverable on the critical path is lagging behind schedule. The cost performance index (CPI) is 1.3. The project manager is able to put
A project's deliverable on the critical path is lagging behind schedule. The cost performance index (CPI) is 1.3. The project manager is able to put the project back on schedule. What happens to the project? Select one.
a. There will be activities performed in parallel.
b. There will be rework.
c. There will be a revised scope.
d. There will be an increase in costs and risks.