A project's work breakdown structure (WBS) provides a detailed framework to follow when creating a definitive estimate of the project's cost. During which phase of
A project's work breakdown structure (WBS) provides a detailed framework to follow when creating a definitive estimate of the project's cost. During which phase of the project lifecycle is the definitive estimate created? O After the Operations and Maintenance phase O At the start of the Implementation phase O In the middle of the Development phase O Near the end of the Concept Planning phase *