A rate of 0 . 4 2 minute per piece is set for a forging operation. The operator works on the job for a full
A rate of minute per piece is set for a forging operation. The operator works on the job for a full
eighthour day and produces pieces. Use a standard hour plan.
How many standard hours does the operator earn?
hours
hours
hours
hours